Interactive Demo — NagaForge Construction ERP  |  All data is sample data. Click any nav item to explore modules ↓
Professional Plan
Demo Residential Tower
NF
Project Dashboard
Active Projects
2
1 active · 1 planning
Workers On Site
47
↑ 3 from yesterday
Budget Utilised
27%
₹1.2Cr of ₹4.5Cr
Open NCRs
1
1 minor · 0 major
Project Progress
Demo Residential Tower27%
G+7 RCC · ₹4.5Cr · Structural phase
Demo Commercial Complex0%
G+3 Steel · ₹2.8Cr · Planning stage
Monthly Expense Trend (₹ Lakhs)
Task Status
3
Done
4
In Progress
5
Todo
1
Urgent
🔴 Safety audit — ScaffoldingUrgent
🟡 Structural drawings — Found.Active
🟢 TMT bars procurementDone
Safety This Month
4
Toolbox Talks
1
Near Miss
0
LTI
PPE Compliance92%
Quality Summary
Cube Tests3 Pass · 0 Fail
QC Inspections3 Pass · 1 Fail
NCRs Open1 Minor
Next InspectionIn 2 days
Projects
Demo Residential Tower
DEMO-PRJ-001
Active
G+7 RCC framed residential tower. IS 456 / IS 13920 seismic design. Mumbai.
Budget
₹4.5 Cr
Spent
₹1.2 Cr
Start
Mar 2026
Deadline
Jun 2027
Overall Progress27%
Demo Commercial Complex
DEMO-PRJ-002
Planning
G+3 steel-framed commercial complex. IS 800:2007 design. Starting in 30 days.
Budget
₹2.8 Cr
Spent
₹0
Start
Jul 2026
Deadline
Dec 2027
Overall Progress0%
Structural Design Engine
IS 456 RCC Design
✅ Beam design (IS 456 Cl. 22-26)
✅ Column design (IS 456 Cl. 39)
✅ Slab design (IS 456 Cl. 24)
✅ Foundation design (IS 1904)
✅ Seismic detailing (IS 13920)
IS 800 Steel Design
✅ Beam design (IS 800 Cl. 8)
✅ Column design (IS 800 Cl. 7)
✅ Connection design
✅ AISC 360-22 check
✅ Eurocode 3 check
Mix Design & BBS
✅ IS 10262 mix design
✅ BBS generation (IS 2502)
✅ Bar bending schedule PDF
✅ Quantity takeoff
✅ BOQ integration
Sample Calculation — RCC Beam (IS 456:2000)
// Beam B1 — Span 6.0m | M25 | Fe415 | 230×450mm
Factored Bending Moment : Mu = 1.5 × 112 = 168 kN·m
Effective Depth : d = 450 - 40 - 10 = 400 mm
Limiting Moment capacity : Mulim = 0.138 × fck × b × d² = 0.138×25×230×400² = 126.96 kN·m
→ Doubly reinforced beam required (Mu > Mulim)
Tension steel (Ast) : 4–20mm dia (Ast provided = 1257 mm²) ✓
Compression steel (Asc) : 2–16mm dia (Asc provided = 402 mm²) ✓
Shear reinforcement : 8mm @ 150mm c/c (IS 456 Cl. 40.4) ✓
// Result: SAFE — All checks passed per IS 456:2000
BIM 3D Model Viewer
Ground Floor
First Floor
Second Floor
Third Floor
Floors 4–7 (Typical)
Plan
3D
Section
Elevation
8 Floors
25.6m Height
4,800 m²
Slab
Column
Beam
Selected Element
Ground Floor
Type: Slab
Material: Concrete M30
Thickness: 150mm
Area: 12.0 × 8.0 = 96 m²
Volume: 14.4 m³
Design Code: IS 456:2000
Status: Complete
Elements Summary
Columns32
Beams64
Slabs8
Walls48
Doors/Windows112
Model Info
Name: DEMO-BIM-001
Version: 1.2
Format: JSON / IFC
Gross Area: 4,800 m²
Height: 25.6 m
Clash Detection
✅ Structural vs Arch — 0 clashes
✅ Structural vs MEP — 0 clashes
⚠️ Arch vs MEP — 2 soft clashes
IFC Export
✅ IFC 2x3 compatible
✅ Revit import ready
✅ Navisworks import ready
Scheduling — CPM / EVM
PV (Planned Value)
₹120L
Week 12
EV (Earned Value)
₹112L
SPI = 0.93
AC (Actual Cost)
₹118L
CPI = 0.95
EAC (Forecast)
₹473L
BAC = ₹450L
Gantt / Activity Schedule
ActivityDurationStartFinishFloatStatusProgress
Site Diary
Today's Site Diary —
Sunny morning / Cloudy afternoon
34°C
68% humidity
Workers on Site
47
Engineers
6
Work Done: Foundation concreting — Column C1-C6 completed. Cube samples taken. Formwork stripped at Basement.
Materials Used: Cement 20 bags · TMT 12mm 400kg · Aggregate 3 cum
Equipment: Tower Crane: 1 · Vibrator: 2 · Concrete Mixer: 1
Instructions: Maintain curing for 14 days post-pour. No loading on new slab for 7 days.
Last 5 Days
1
Today
Foundation concreting C1-C6
2
Yesterday
Rebar fixing — GF columns
3
2 days ago
Formwork striking — Basement
4
3 days ago
RCC column pour — Grid A
5
4 days ago
Brickwork — External walls
Equipment & Plant
EquipmentNo.CategoryOwnershipHire Rate/dayLast ServiceNext ServiceStatus
Tower Crane TC-5013EQ-001CraneHired₹8,00028 May 202627 Jul 2026Active
Concrete Pump CP-36EQ-002PumpHired₹12,00014 Jun 202614 Jul 2026Active
Excavator JCB 3DXEQ-003ExcavatorOwned01 Jun 202601 Aug 2026Maintenance
Generator DG 125kVAEQ-004GeneratorOwned15 May 202615 Aug 2026Active
Workers & Attendance
Total Workers
47
On project
Present Today
44
93.6% attendance
Overtime Today
8
workers
Absent
3
Prior approval
IDNameRoleCheck InCheck OutHoursOTStatus
W001Rajesh KumarEngineer08:0017:309.5h1.5hPresent
W002Priya SharmaArchitect08:1517:008.75h0.75hPresent
W003Mohan DasForeman07:4518:3010.75h2.75hPresent
W004Sunita PatelSafety Officer08:0017:009h1hPresent
W005Vikram SinghSite Manager07:3018:0010.5h2.5hPresent
W006Anita IyerEngineerAbsent
Quality Control
Cube Test Results
SampleElementGradefck MPaResult
CUBE-001Column C1-GFM3031.2Pass
CUBE-002Slab S1-GFM2526.5Pass
CUBE-003Beam B1-GFM3029.8Pass
QC Inspections
No.TypeElementResult
QCI-001RebarColumns GFPass
QCI-002FormworkSlab 1FPass
QCI-003Pre-pourSlab 1FPass
QCI-004BrickworkExt WallFail
NCR — Non-Conformances
NCR-001
Brick masonry — incorrect bond
Minor
External Wall, Ground Floor · Raised: QC Engineer
Action: Demolish and rebuild with English bond
Open · Due in 5 days
QC Checklist — QCI-001 (Rebar Inspection, Columns GF)
#Check PointReferenceRequirementActualStatus
1Bar dia and spacing correctIS 456 Fig 5As per drawingVerifiedPass
2Cover blocks in placeIS 456 Cl.26Min 40mm clear40–45mmPass
3Laps and splices adequateIS 456 Cl.26Ld = 47d50d providedPass
4Formwork joints sealedIS 456No gapsSealedPass
HSE Safety
LTI-Free Days
127
0 Lost Time Injuries
Toolbox Talks
4
This month
Open Permits
2
Height work + excavation
Risk Assessments
5
All reviewed
Recent Toolbox Talks
Working at Height — Fall Prevention
40 attendees · 20 min · Safety Officer
Concrete Pouring Safety
45 attendees · 20 min · Safety Officer
Crane Safety & Exclusion Zones
38 attendees · 20 min · Safety Officer
Risk Assessment Register
ActivityHazardScoreLevel
Height WorkFall from height20High
Concrete PourFormwork failure15High
Crane OpsLoad drop10Medium
ExcavationCave-in8Medium
ElectricalElectrocution8Medium
Permits to Work
Permit No.TypeTitleLocationStatus
PTW-001Height WorkWorking at Height — Column L3Columns A1-A6, Level 3Approved
PTW-002Hot WorkWelding — Column base platesBasement, Grid CClosed
PTW-003ExcavationExternal utility trenchNorth boundaryPending
Commercial & BOQ
Contract Value
₹4.5Cr
Billed to Date
₹1.2Cr
Received
₹0.9Cr
Outstanding
₹0.3Cr
Bill of Quantities — Civil Works (Extract)
ItemDescriptionUnitQtyRate (₹)Amount (₹)
1.1Earthwork in excavation for foundationcum4202801,17,600
1.2PCC M10 — 75mm thick blindingcum284,8001,34,400
1.3RCC M30 — Raft foundationcum1858,20015,17,000
1.4Tor Steel Fe415 in foundationsMT2868,00019,04,000
2.1RCC M30 — Columns GFcum229,5002,09,000
2.2RCC M25 — Slabs GFcum588,8005,10,400
Sub-Total (Civil)44,92,400
Invoices
Invoice No.ClientIssue DateDue DateAmountTaxTotalPaidStatus
INV-DEMO-0001Demo Holdings13 Jun 202613 Jul 2026₹50,00,000₹9,00,000₹59,00,000₹0Sent
INV-DEMO-0000Demo Holdings01 Apr 202601 May 2026₹30,00,000₹5,40,000₹35,40,000₹35,40,000Paid
Documents
TitleTypeFileVersionUploaded ByApproval
Structural Design Report — FoundationDesign ReportSTRUC-001-Rev0.pdf1.0Rajesh KumarApproved
Architectural Drawing — GF PlanDrawingARCH-GF-Rev2.dwg1.0Priya SharmaApproved
Structural Drawing — Column LayoutDrawingSTRUC-COL-Rev1.dwg1.0Rajesh KumarPending
IS 456 Concrete Mix Design M30Test ReportMIXDES-M30-001.pdf1.0QC EngineerApproved
Safety Management PlanSafety DocSMP-Rev1.pdf1.0Safety OfficerApproved
Project Quality PlanQuality PlanPQP-Rev0.pdf1.0QC EngineerPending
BOQ — Civil WorksCommercialBOQ-Civil-Rev2.xlsx1.0Finance MgrApproved
Reports & Analytics
Project Progress Report
Gantt, milestones, EVM, S-curve
PDF Export
Monthly HSE Report
Incidents, toolbox talks, PTWs, KPIs
PDF Export
Quality Control Report
Cube tests, inspections, NCR log
PDF Export
Financial Report
Budget vs actual, cash flow, BOQ
PDF Export
Labour Productivity Report
Attendance, overtime, manday analysis
PDF Export
Structural Calculation Report
IS 456 / IS 800 design calculation PDFs
PDF Export